The former AT&T campus at 3033 Chain Bridge Road in Oakton is cleared for housing and retail in Fairfax County’s long-range plan, but no project has been approved yet. Supervisors changed the Comprehensive Plan on March 18, 2025, for a proposal FFXnow reported at 854 homes and about 110,850 square feet of retail. The rezoning that would lock in the details was still under county staff review in the latest report we found, and a county traffic study of the area is still underway.

Quick summary
- Site: 33 acres at Chain Bridge Road (Route 123) and Jermantown Road, currently an early-1980s office building and parking.
- Approved: a Comprehensive Plan amendment (SSPA 2023-II-1F), adopted March 18, 2025.
- Not yet approved: the rezoning application, RZ/FDP 2023-PR-00020, filed by developer EYA.
- Proposal as reported: 854 homes and about 110,850 square feet of retail and service space.
- Traffic: the county’s Oakton Congestion and Safety Study held a public meeting Oct. 5, 2026; no road changes have been approved.
What Fairfax County approved in 2025
On March 18, 2025, the Board of Supervisors unanimously approved a Comprehensive Plan change that allows mixed-use development on the site, with Springfield District Supervisor Pat Herrity absent, according to FFXnow. The county lists the change as Plan Amendment SSPA 2023-II-1F. The site is in the Providence District and sits within the Flint Hill Suburban Center planning area.
Supervisors also adopted the Planning Commission’s recommendation to lower the maximum floor area ratio from 1.0 to 0.88, FFXnow reported. (The county’s summary page still describes the amendment as considering “up to 1.0 FAR,” so check the adopted text if that figure matters to you.) The numbers have shifted before: in October 2023, FFXnow reported that EYA had scaled its concept back from 1,500 homes in the original nomination to 1,000. By the 2025 vote, the reported figure was 854.
What is still pending: the rezoning
The plan change sets the rules. It does not approve buildings. The county’s own plan page says the recommendation should not be construed as a favorable recommendation on the zoning application. That application, RZ/FDP 2023-PR-00020, seeks approval of single-family attached and multifamily homes plus community-serving retail, and it is where the final home count, layout, roads and tree preservation get decided.
FFXnow reported on March 16, 2026 that the rezoning was under review by county staff. We did not find a newer update or a scheduled hearing date as of Nov. 26, 2026, so treat the timing as open. As Supervisor Dalia Palchik put it after the 2025 vote, “We’re just at the Comprehensive Plan level.”
The Oakton traffic study
To address traffic concerns, the Board set aside $425,000 for a study of roughly a mile of Chain Bridge Road near Jermantown Road. It now runs as the Oakton Congestion and Safety Study, led by the Fairfax County Department of Transportation. The county’s study map covers about 20 intersections and site entrances along Chain Bridge Road, Jermantown Road, Blake Lane, Hunter Mill Road, Courthouse Road and Edgelea Road.
In March 2026, the county narrowed resident suggestions to 10 options, including connecting Miller Road and Jermantown Road near the Cross County Trail, a roundabout on Hunter Mill Road, and a new traffic signal at Blake Lane and Hibbard Street. The county said all 10 need further study and VDOT approval, and an FCDOT spokesperson said more than one concept could move forward. The county’s page says a public meeting was held Oct. 5, 2026, the comment period has closed, and the study report will include planning-level cost and schedule estimates. No release date is posted.
What this means for Oakton homeowners
Nothing changes on the ground yet. Redevelopments of this size in Northern Virginia typically take years to move from plan to rezoning to construction, and this one has already been resized twice. If you own near Route 123, Jermantown Road or Blake Lane, the two things worth watching are the rezoning hearing schedule, which is when the home count and site design become official, and the traffic study report, which will show which road changes the county pursues. Both can affect commute patterns and local shopping options for years.
For a wider view of the area, see my Oakton VA real estate guide and the Oakton development tracker. Wondering how projects like this factor into your home’s value? My Oakton home value tool is an easy place to start.
Frequently asked questions
Is the Oakton AT&T site redevelopment approved?
Only the first step. The Fairfax County Board of Supervisors approved a Comprehensive Plan amendment for the site on March 18, 2025. The rezoning that would approve an actual project, RZ/FDP 2023-PR-00020, was still under county staff review as of FFXnow’s March 2026 report, and no hearing date had been published as of Nov. 26, 2026.
How many homes are proposed at 3033 Chain Bridge Road?
FFXnow reported in March 2025 that the developer, EYA, proposed 854 homes and about 110,850 square feet of retail and service space on the 33-acre site. Earlier concepts were larger, and the final numbers could change during the rezoning.
What is the Oakton Congestion and Safety Study?
It is a Fairfax County Department of Transportation study that came out of the Board’s approval of the AT&T plan amendment. It looks at intersections along Chain Bridge Road, Jermantown Road, Blake Lane, Hunter Mill Road and nearby streets. The county held a public meeting on Oct. 5, 2026, the comment period has closed, and the final report will include planning-level cost and schedule estimates.
Has the county approved any Oakton road changes?
No. In March 2026 the county presented 10 community-suggested options, such as a new signal at Blake Lane and Hibbard Street, and said all of them require further study and approval by VDOT.
Sources
Fairfax County, “Plan Amendment SSPA 2023-II-1F; AT&T Oakton” (adoption date, site, rezoning application number).
Fairfax County Department of Transportation, “Oakton Congestion and Safety Study” (study scope, Oct. 5, 2026 meeting, comment period, report contents).
FFXnow, March 20, 2025 (vote, 854 homes, retail square footage, FAR, $425,000 study).
FFXnow, March 16, 2026 (rezoning status, 10 road options, VDOT approval).
FFXnow, Oct. 9, 2023 (earlier housing counts).
Details current as of Nov. 26, 2026. Unit counts and retail space are as reported by FFXnow and may change during the rezoning. Check Fairfax County for the latest status.